1. 外商驻杭州办事处的跟单员跟踪A厂一批衣夹的生产,订单数量为4216540pcs,交货期为七月八号, A厂从六月五号(周一)开始生产。正常一周工作5天,每天2个班次,每班工作8个小时,该跟单员编制的生产进度表如下,由于6月28日30%的设备突然坏掉,第二天仍无法修复,为了准时交货,跟单员与该厂商定,于6月30日开始每班工作时间延长一个小时,并且7月1日和2日加班两天,请填好余下几天的生产进度表。
Daily Capacity Summary
Product: cloth peg order quantity: 4216540pcs expanded finished date: July, 8,2009
Date |
Daily Output |
Total Output |
Qty
Still left |
Production
Days left |
Average Qty need to produce per left day |
5 Jun |
172000 |
172000 |
4044540 |
24 |
168522 |
6 Jun |
170000 |
342000 |
3874540 |
23 |
168458 |
7 Jun |
171000 |
513000 |
3703540 |
22 |
168342 |
… |
… |
… |
… |
… |
… |
27 Jun |
168800 |
2889300 |
1328240 |
8 |
166030 |
28 Jun |
118800 |
3008100 |
1208440 |
7 |
172634 |
29 Jun |
118900 |
3127000 |
1089540 |
6 |
181590 |
30 Jun |
138000 |
|
|
|
|
1 Jul |
139000 |
|
|
|
|
2 Jul |
138000 |
|
|
|
|
3 Jul |
137000 |
|
|
|
|
4 Jul |
138000 |
|
|
|
|
5 Jul |
137000 |
|
|
|
|
6 Jul |
139000 |
|
|
|
|
7 Jul |
123540 |
|
|
|
|
|